In Court of Auditors is judged to be the Thursday, November 19 the project «Water Supply Infrastructure Interconnection Networks of the Municipality of Kythira», with a budget of 1.5 million euros, which was awarded without an open bidding process, citing urgency following the 2025 fire. The 7th Division is examining the case as part of a pre-contractual audit, that is, before the contract with the contractor is signed.
The municipality itself describes the case as «particularly serious and complex». Nevertheless, on November 16, the Municipal Committee commissioned (Decision 133/2026) his representation to two lawyers in Athens at a total cost of 823.36 euros including VAT, that is, only the mandatory advance payment receipts, «without any additional attorney’s fees.».
The Project and the Cost
The project provides for 13,445 meters of piping which will connect the reservoirs in Diakofti, Paleopolis, Chorokampos, and Georga, as well as the Kapsali desalination plant, to the reservoirs in Koukos and Chora. The budget amounts to approximately 112,000 euros per kilometer (81,000 euros for the work alone). According to the request for proposals, of the 1.5 million euros, 1,084,457 euros are for the work, 195,202 for general expenses and the contractor’s profit (18%), and 191,949 for «contingencies» (15%).
The funding comes from a program of the Ministry of Environment and Energy for the water scarcity and not for the fire-affected areas: 1,350,000 euros from the Public Investment Program and 150,000 euros from the municipality's funds. The decision on inclusion (December 30, 2025) describes the project as an improvement to the network’s operation and makes no mention of the fire. The phrase «for the fire-affected areas» appears for the first time in April 2026, in the Permit to cross forest land. The physical object does not name any fire-damaged villages: according to the Decision 71/2026, water will be supplied to Aroniadika, Friligianika, Myrtidia, and Karvounades through existing networks.
Awarding a contract without an open competitive bidding process
- November 27, 2025: The project study is complete.
- December 30, 2025: funding is approved (Ministry of Environment and Energy Integration Decision).
- June 16, 2026: the Municipal Committee (Decision 71/2026) approves a negotiated procedure without publication, citing urgency.
- June 26, 2026: Three companies, all from Attica, are invited to bid: ZITAKAT ATEBE, PAKTOSI TECHNIKI IKE, and CHOROTECHNIKI ATE.
- July 14, 2026: Sales are starting, with discounts 3%, 2%, and 1%.
- July 30, 2026: ZITAKAT has been selected as the contractor (Decision 94/2026), with a bid of 1,455,569.27 euros, excluding VAT.
From the completion of the study to the decision on the «emergency,» the following period elapsed: almost seven months, during which time an open competitive bidding process could have been held. (The call for bids cites Article 32 of Law 4412/2016, while Decision 71/2026 cites Article 269.).
The Opposition's Warnings
This isn't a new issue. Kythera.News had already reported on it as of June 30 point out that a project for which a study had been completed in November was suddenly designated «urgent.» On July 28, the faction «Free Kythira» requested the study to conduct a financial and technical audit, arguing that the cost per kilometer significantly exceeds the national average, that its reservations expressed in May regarding the urgency of the matter remained unaddressed, and that the three companies are the same ones that have been undertaking most of the island’s public works projects for years.
The study was never submitted. The municipal council member from the minor opposition party Andreas Mariatos reported to Kythera.News on November 16 that, although it had been requesting it since July 28, the members of the Municipal Committee were provided only with a brief, five-page «Technical Description.» At the same meeting, written questions were submitted regarding the composition of the legal team and its compensation.
Kythera.News at the Court of Auditors
On November 15, Kythera.News publicly posed questions to the municipal authorities. We asked, among other things, that the following be made public: the document or ruling of the Court of Auditors that referred the case to the 7th Division, that is, what objections were raised regarding the legality of the contract award, and to provide us with the complete technical study of the project. We also asked about the «urgency,» the selection of the three firms, and the 1% to 3% discounts, as well as the criteria for selecting the attorneys. The Municipal Authority He didn't answer any of them. That is why, on November 17, we contacted directly the Court of Auditors, with copies sent to the Mayor, the President of the City Council, and the leaders of the political groups. We requested:
- Copy of the Panel's Decision (or the comment document) that was submitted to the municipality regarding the project.
- Update on the status of the process. If the case being heard is request for revocation of the Municipality; this means that the Court has already identified issues of legality in the contract award, and the Municipality is attempting to overturn this ruling.
Why aren't the documents being provided?
The key question that arises from this whole situation is simple: Why won't the municipal government provide the documents for a public works project worth 1.5 million euros? The full study has not been provided either to the opposition—which has been requesting it since July 28—or to Kythera.News. The members of the Municipal Committee were asked to vote with only a five-page «Technical Description» in hand. Furthermore, the document from the Court of Auditors that referred the case to the 7th Division has not been disclosed to anyone, even though the Municipality itself characterizes the case as «particularly serious.».
These are not internal or confidential documents, but rather a study of a project funded with public money—including 150,000 euros from the municipality’s funds— and a court’s ruling on the matter. The right of access to public documents is guaranteed by the Constitution (Article 5A) and by the Code of Administrative Procedure (Article 5 of Law 2690/1999), while municipal council members—and even more so the members of the decision-making body—need a complete picture in order to vote responsibly. What is it that the municipal government doesn't want the council members, the press, and the public to see?
The questions raised publicly by Kythera.News
- Why aren’t the full report and the document from the Court of Auditors being provided to city council members, the press, and the public?
- Why was the case referred to the 7th Division, and what objections did the Court of Auditors raise?
- What was the «urgency,» when the study had been ready since November and the funding had been secured since December?
- What criteria were used to select the three companies, and how were the discounts ranging from 1% to 3% deemed reasonable?
- Why hasn't the full study been provided to the opposition and to the media outlet that requested it?
- What criteria were used to select the attorneys? Is there a provision for additional compensation in the future?
- What happens if the Congress does not approve the agreement? Is there a plan to ensure that the funding is not lost?
Kythera.News will publish any response it receives (to date, only Mr. Mariatos has contacted us), as well as the response from the Court of Auditors, and will follow the developments.
Sources (Diafania): Executive Committee Decision No. 71/2026 · Executive Committee Decision No. 94/2026 · Executive Committee Decision No. 133/2026 (Representation before the Court of Auditors) · Ministry of Environment and Energy Integration Decision · Approval for Passage Through a Forest Area · Approval from the Ephorate of Antiquities
Read more: A 1.5-million project with the «scent» of a direct award in Kythira and «Free Kythira»: They File a Request for a Financial and Technical Audit of the 1.5 Million Euro Project